Technical Assignment #1
This assignment is a look at the basics of the buiding and the construction process of the building. This report contains infor on the project schedule, building systems, square foot cost, site conditions and layout, owner, project delivery, and key players.
Technical Assignment #2
This assignment is a look at the detailed project schedule, the site plan for three critical phases of the project, a structural systems and general conditions estimate, and last an overview of the PACE Roundtable.
Technical Assignment #3
This assignment is a project manager interview to discuss constructability challanges, schedule acceleration scenarios, and value engineering topics. I also made my own ovservation on problems on the project and technical analysis methods for the basis for my final thesis proposal.
|